UNIT I SUB STRUCTURE CONSTRUCTION
Box jacking - Pipe jacking - Under water construction of diaphragm walls and basement - Tunneling techniques - Piling techniques - Driving well and caisson - sinking cofferdam – cable anchoring and grouting - Driving diaphragm walls, Sheet piles - Laying operations for built up offshore system - Shoring for deep cutting - Large reservoir construction - well points – Dewatering  for underground open excavation.

UNIT II SUPER STRUCTURE CONSTRUCTION FOR BUILDINGS
Vacuum dewatering of concrete flooring – Concrete paving technology – Techniques of construction for continuous concreting operation in tall buildings of various shapes and varying sections – Erection techniques of tall structures, Large span structures – launching techniques for heavy decks – in-situ prestressing in high rise structures, Post tensioning of slab- aerial transporting – Handling and erecting lightweight components on tall structures.metal deck concrete flooring/roofing

UNIT III CONSTRUCTION OF SPECIAL STRUCTURES
Erection of lattice towers - Rigging of transmission line structures – Construction sequence in cooling towers, Silos, chimney, sky scrapers - Bow string bridges, Cable stayed bridges  Launching and pushing of box decks – Construction of jetties and break water structures – Construction sequence and methods in domes – Support structure for heavy equipment and machinery in heavy industries – Erection of articulated structures and space decks, precast concrete erection/temporary propping/connections.

UNIT IV REHABILITATION AND STRENGTHENING TECHNIQUES 
Seismic retrofitting - Strengthening of beams - Strengthening of columns - Strengthening of slab - Strengthening of masonry wall, Protection methods of structures, Mud jacking and grouting for foundation – Micro piling and underpinning for strengthening floor and shallow profile - Sub grade water proofing, Soil Stabilization techniques.

UNIT V DEMOLITION 
Demolition Techniques, Demolition by Machines, Demolition by Explosives, Advanced techniques using Robotic Machines, Demolition Sequence, Dismantling Techniques, Safety precaution in Demolition and Dismantling.

REFERENCES:
1. Jerry Irvine, Advanced Construction Techniques, CA Rocketr, 1984
2. Patrick Powers. J., Construction Dewatering: New Methods and Applications, John Wiley & Sons, 1992.
3. Peter.H.Emmons, “Concrete repair and maintenance illustrated”, Galgotia Publications Pvt. Ltd., 2001.Press, 2008.
4. Robertwade Brown, Practical foundation engineering hand book, McGraw Hill Publications, 1995.
5. Sankar, S.K. and Saraswati, S., Construction Technology, Oxford University Press, New Delhi, 2008.

Search by Students:

Cn5201 Advanced Construction Techniques   Notes
Cn5201 Advanced Construction Techniques  Syllabus
Cn5201 Advanced Construction Techniques  Book
Cn5201 Advanced Construction Techniques  Papers
Cn5201 Advanced Construction Techniques  2 13 15 Marks  Pdf Ppt

Cn5201 Advanced Construction Techniques   Question Bank With Answers




No comments:

Post a Comment